Owner: City of Reading
Status of the Project: Finish
Construction Started: January 2016
Construction Completion Date: Completed end of 2019
Cost: $42,580,000
Owner: City of Reading
Status of the Project: Finish
Construction Started: January 2016
Construction Completion Date: Completed end of 2019
Cost: $42,580,000
As part of the spandrel arch rehab the contract also provided aesthetic coating and new lighting across and under the entire structure.
Rehabilitation of the concrete spandrel arches included
extensive removal limits that created complex concrete forming
of new floor beams as well as a precast decorative parapet.